@@ -2515,9 +2515,9 @@ We are so thankful for every contribution, which makes sure we can deliver top-n
25152515

25162516
### When the Developers determine that they will not be able to finish the complete forecast, who needs to be present when reviewing and adjusting the Sprint work selected? (choose the best answer)
25172517

2518-
- [x] The Scrum Master and the Developers.
2518+
- [ ] The Scrum Master and the Developers.
25192519
- [ ] The Product Owner and all stakeholders.
2520-
- [ ] The Product Owner and the Developers.
2520+
- [x] The Product Owner and the Developers.
25212521
- [ ] The Scrum Master project manager and the Developers.
25222522

25232523
**[⬆ Back to Top](#table-of-contents)**