Move transfer provisioning phase in data-plane

Decision

We will move the transfer provisioning and deprovisioning phases in the Data-Plane

Rationale

At the moment the provisioning and deprovisioning phases are managed by the Control-Plane, specifically in the TransferProcessManager. This is not optimal because it's making the Control-Plane to need knowledge on how to deal with specific data flow protocols, while it should be agnostic.

Making the Data-Plane handling those will ensure better responsibilities separation and simplify the transfer process logic.

Approach

The data-plane signaling interface will have an additional method (prepare) and, with the other methods (start, suspend, terminate) will have a common behavior, on which the provision/deprovision async operation will be eventually triggered on the call, and the caller (the control plane) will be immediately aware if the async operation has been triggered, if not the TransferProcess state machine can continue with the standard flow, otherwise the entity will be put in an intermediate state *-REQUESTED, waiting for a callback from the data plane. If the callback is successful, the state machine will continue the standard flow, otherwise there will be a retry mechanism put in place. The state machine will also monitor "stale" *-REQUESTED states, to prevent potential data-plane failures.

The flow pattern in the different cases has been represented in this table:

Starting state Type Signaling Method Async operation State if async operation happen State if async operation NOT happen
INITIAL CONSUMER prepare provisioning PREPARATION_REQUESTED REQUESTING
INITIAL PROVIDER start provisioning STARTUP_REQUESTED STARTING
STARTED suspend deprovisioning SUSPENSION_REQUESTED SUSPENDING
STARTED terminate deprovisioning TERMINATION_REQUESTED TERMINATING

The DataFlow will get the new PROVISION* and DEPROVISION* states and the state machine will treat them the same way the TransferProcessManager is treating them.

Plan

To avoid disruptions for users during upgrade the refactoring will be made in incremental way in this order:

  • add provisioning process on the DataPlaneManager with additional states and transitions (the services used will be the same, switching TransferProcess to DataFlow as target entity)
  • add deprovisioning process on the DataPlaneManager with additional states and transitions (the services used will be the same, switching TransferProcess to DataFlow as target entity)
  • remove provisioning process from the TransferProcess
  • remove provisioning process from the TransferProcess
  • deprecation of the *PROVISION* states in `TransferProcessStates, to be deleted after some versions

Assumptions

  • the provisioner can modify the source/destination addresses, it is expected that the eventual new addresses are supported by the data-plane instance that took care of the provisioning, otherwise it will cause failure in the transfer startup.