Revision Review processes backlog

Ainhoa Gracia edited this page Aug 21, 2013 · 13 revisions

Project BackLog to complete the Revision/Review processes

ID Chapter of the QAP Description Responsible for implementation Status of implementation Deadline for Implementation Reviewers Priority
0 All Update the current ‘Review Process’ to adapt it to ‘Revision process’ and prepare a new document for the ‘Review Process’ SQS Done 24.05.2013 All High
1 All Delivery of Docs.0 for Review to the community SQS Done 24.05.2013 All High
2 All Prepare a summary of the ‘Revision Process’ and ‘Review process’ SQS Done 27.05.2013 All High
3 All Delivery of Doc.3 for Review to the community SQS Done 27.05.2013 All High
4 All Deadline for receiving comments SQS Done 30.05.2013 All High
5 All Comments implemented SQS Done 06.06.2013 All Medium
6 Planned Reviews Template design for planned reviews SQS In progress 03.07.2013 All Medium
7 All Final publication SQS ToDo - Medium