For each data hall, this answers one question: can the hall start its next commissioning level now, and if not, why not? It reads the hall's assets from NetBox, the commissioning records, the punch list and a capacity figure, and gives a ready / conditional / not-ready verdict. Every verdict comes with its reasons.
Synthetic practice model. Every hall, device, test record and punch item in this repo is made up. The asset list is shaped like a NetBox export and a few device types are real entries from NetBox's device-type library, but the site doesn't exist. This is a model of how readiness gates can be checked, not a record of real data-center commissioning work.
Part of a small project-controls toolkit: project-controls-dashboard, schedule-health-analyzer, change-control-register, risk-trend-tracker, project-controls-reporting-engine, recovery-scenario-planner, facility-status-digital-twin, commissioning-readiness-gate (this repo).
My delivery work has been automation systems on offshore drilling programmes, where FAT, SAT and release gates decided when a system was allowed to move to the next stage. I haven't commissioned a data center. This repo takes that gate discipline and applies it to the L1 to L5 commissioning sequence data halls use, as practice.
- Not a DCIM tool. Assets are read from NetBox, never edited, and nothing here tracks rack elevations, cabling or asset lifecycle.
- Not an MEP or electrical engineering assessment. The capacity check compares recorded numbers; it doesn't model anything.
- Not a commissioning authority's tool. It doesn't hold test scripts or test results, only whether each level is recorded closed and signed.
- Not evidence of data-center delivery experience (see above).
Before a data hall can move to its next commissioning level, someone has to check that every piece of equipment has closed the levels before it, that nothing on the punch list blocks the step, and, from first energisation onward, that the IT load the hall is designed for fits the power and cooling actually provisioned. That check usually lives across a Cx tracker, a punch list spreadsheet and an asset register, and gets done by hand the week before the milestone.
Each hall has a target: the next level it is planned to start, with a
planned date (data/hall_gates.csv). The gate rules (src/rules.py) then
check the hall against that target:
| Rule | Effect | What it checks |
|---|---|---|
| SEQUENCE | blocks | A level recorded closed on a device while an earlier level on that device isn't. No skipping. |
| PREREQ | blocks | Every device has closed every level before the target. For IST (L5), that means every device's L4. A closed record with no signature doesn't count. |
| WAIVED | conditional | A PREREQ gap covered by a waiver. Only when waivers are switched on in config/gate.yaml (off by default); never better than conditional. |
| PUNCH_A | blocks | Open category A punch items in the hall. |
| PUNCH_B | conditional | Open category B items: must close before handover, don't stop the next level. |
| PUNCH_C | info | Open category C items, reported only. |
| CAPACITY | blocks | From the energisation level (L3) onward: the hall's design IT load, summed from its racks, above provisioned power or provisioned cooling. |
Any blocking reason gives not-ready, otherwise any conditional reason gives conditional, otherwise ready.
flowchart LR
A[NetBox CSV export<br/>data/netbox/] --> L[inputs.py<br/>fixed schema]
B[Live NetBox, optional<br/>netbox_adapter.py via pynetbox] --> L
C[Commissioning records,<br/>punch list, capacity,<br/>hall gates, waivers<br/>data/*.csv] --> L
Y[config/levels.yaml<br/>config/gate.yaml] --> R
L --> R[rules.py<br/>verdict + reasons per hall]
R --> O[report.py]
O --> M[assets/report.md]
O --> P[assets/readiness_matrix.png]
The CSV export and the live adapter produce the same schema, and a test checks that they do on the same assets, so the rules can't tell the two apart. Nothing is ever written to NetBox.
Running gate.py against the sample data:
Commissioning readiness as of 2026-10-05 (site DC-Sample, 3 halls)
DH1 next: L5 Integrated systems testing (IST), planned 2026-11-02 (28 days) READY
DH2 next: L5 Integrated systems testing (IST), planned 2026-11-16 (42 days) CONDITIONAL
- PUNCH_B: 2 open category B punch items (P-201, P-202)
DH3 next: L3 Pre-functional and start-up, planned 2026-10-19 (14 days) NOT READY
- SEQUENCE: DH3-CRAH-02: L3 recorded closed while L2 is open
- PREREQ: DH3-UPS-01: L2 open, needed before L3
- PREREQ: DH3-CRAH-02: L2 open, needed before L3
- PREREQ: DH3-PDU-R02: L2 closed but unsigned, needed before L3
- PUNCH_A: 1 open category A punch item (P-301)
- CAPACITY: design IT load 300 kW exceeds provisioned cooling 280 kW
Wrote assets/report.md
Wrote assets/readiness_matrix.png
DH3 is the interesting one: two weeks from first energisation, one unit already has its start-up recorded as done while its installation check is still open, one signature is missing, and the racks it's designed for need more cooling than the hall has. Each of those would normally surface in a different document. The full report, including info-level reasons and level progress per hall, is in assets/report.md.
The default levels in config/levels.yaml:
| Level | Name | Scope |
|---|---|---|
| L1 | Factory acceptance | Each piece of equipment, at the factory |
| L2 | Delivery and installation verification | Each piece of equipment, on site, unpowered |
| L3 | Pre-functional and start-up | Each piece of equipment, first power-up (energisation) |
| L4 | Functional performance testing | Each system against its sequence of operation |
| L5 | Integrated systems testing (IST) | The whole hall together at simulated design load, with failure scenarios |
The L1 to L5 numbering is industry convention, not a standard, and sources don't fully agree on what each level covers. One describes L2 as site acceptance testing, another as delivery and static inspection, and some firms use levels 0 to 6. So the levels are a config file: edit it to match the project's own Cx plan. The gate logic only uses their order and which level is energisation. Sources for the defaults:
- Anvilfield: data center commissioning levels and process field guide
- A3A Engenharia: data center commissioning, L1 to L5 levels, IST and acceptance
- PCM: data center commissioning levels, L1 to L5 explained
- Archdesk: data center commissioning, L1 to L5 explained
- The level definitions are a generic convention, not a project's Cx plan.
- Strict sequencing (no level closes before the one below it) is stricter than many real projects run, where some L3 work overlaps late L2 items. Waivers exist for that, but they're off by default.
- "Closed" means a status and a signature. Real closure depends on the evidence behind it (witnessed scripts, load bank records, BMS and EPMS trend data), none of which is modelled here.
- IST is recorded as one hall-level pass or fail. It isn't derived from test data, and failure scenarios aren't represented.
- The capacity check sums design IT load per rack and compares it with two provisioned numbers. It ignores diversity, redundancy topology (N+1, 2N), mechanical load, and load bank planning.
- Punch categories are simplified to A (blocks the next level), B (before handover) and C (cosmetic). Real punch lists often grade differently.
- Big plant (switchboards, UPS modules, CRAH units) is listed as NetBox devices with generic device types. Plenty of sites don't track that plant in NetBox at all.
- Sign-off roles in
levels.yamlare placeholders.
- Size-tested with
benchmarks/size_test.pyby repeating the sample halls, on a 2018 laptop (Intel i7-8750H, Python 3.14), single runs, so treat the numbers as a guide: 30 halls (210 devices) run in about 2 seconds, 300 halls in about 6 and 1,000 halls in about 20, using around 150 MB. The readiness chart shows the 30 halls furthest from ready; report.md covers every hall.
pip install -r requirements.txt
python gate.pyInputs, all keyed to NetBox IDs:
data/netbox/devices.csv,data/netbox/racks.csv: NetBox's own table export (Devices and Racks lists, Export > Current view) with at least ID, Name, Status, Site, Location, Rack, Role, Manufacturer and Type visible. Each NetBox Location is treated as one hall.data/commissioning.csv: one row per device and level (device ID blank for the hall-level L5), with status, who signed and when.data/punch_list.csv,data/hall_capacity.csv,data/rack_design_load.csv,data/hall_gates.csv,data/waivers.csv.config/levels.yaml(levels and their order),config/gate.yaml(status date, site, waivers on or off).
To read devices and racks from a live NetBox instead of the export, install pynetbox and point the tool at it (read-only; the token comes from the environment):
pip install pynetbox
NETBOX_TOKEN=... python gate.py --netbox-url https://netbox.example.com --site-slug dc-sampleThe tests run the adapter against NetBox-shaped API responses in
tests/fixtures/netbox_api/, so CI doesn't need a NetBox server.
To see how it copes with sites with more halls, run python benchmarks/size_test.py. It prints run time and peak memory at each size.
It's a hand-run check, not part of the test suite; measured numbers are
under Limitations.